Our plain-English summary of Bernard v. Brookfield Prop. Corp. (New York Supreme Court, September 23, 2010).
Shelly Bernard sued several defendants in 2008, claiming asbestos-related injury. She said she was exposed to asbestos dust while working as a consultant for Salomon Brothers on the 28th floor of 55 Water Street in Manhattan from 1985 to about February 1988, during renovations and construction. She became sick with ovarian cancer in 2007 and has been diagnosed with mesothelioma. Defendant Colgate Palmolive filed cross claims against Ruderman, a structural engineering firm that worked on the building. Ruderman moved to dismiss because no one had served the 90-day notice of claim that CPLR 214-d requires for claims against licensed engineers over work done more than ten years earlier. The court denied Ruderman's summary judgment request as premature, because Ruderman had not answered. It granted dismissal of the claims and cross claims against Ruderman, without prejudice to refiling in compliance with CPLR 214-d and CPLR 205. It denied Colgate's request to treat its late notice as timely, because Colgate offered no expert affidavit of negligence. Plaintiff did not oppose the motion.
We wrote this summary from the court's opinion with the help of AI. It is not the court's wording, and it is not legal advice. The full opinion is below.
You don't need the product names or old records. No fee unless we recover compensation for your family.
The decision
- Court: New York Supreme Court
- Decided: September 23, 2010
- Citation: 2010 NY Slip Op 32666(U)
- Docket: No. 107211/2008, Seq. No. 003
- Stage: Motion to dismiss
- State: New York
Outcome. The court granted defendant Ruderman's motion to dismiss the complaint and cross claims against it, without prejudice to recommencement, denied its premature summary judgment request, and denied Colgate's cross motion to treat its late notice of claim as timely served.
What the court held. Under CPLR 214-d and CPLR 3211(h), claims against a licensed engineering firm for work done more than ten years earlier must be dismissed if no notice of claim was served 90 days before suit and compliance was not pleaded, unless the claimant shows a substantial basis, such as expert proof, that the firm was negligent. Dismissal for non-compliance is without prejudice to a new action under CPLR 205.
Issues decided: Trial Procedure and Discovery.
The people and their exposure
- Shelly Bernard: ovarian cancer, mesothelioma
| Who | Work | Where | When | Products |
|---|---|---|---|---|
| Shelly Bernard | consultant for Salomon Brothers; worked near others using it | 55 Water Street, New York, New York | 1985-1988 |
The defendants
- The Office of James Ruderman, LLP (contractor)
- Colgate Palmolive Corporation
The court's opinion
The text below is Google Scholar's copy of the court's opinion, a public record. Numbers in brackets, such as [*921], mark where each page of the printed reporter begins.
2010 NY Slip Op 32666(U)
SHELLY BERNARD, Plaintiff,
v.
BROOKFIELD PROPERTIES CORPORATION, etal., Defendants.
No. 107211/2008, Seq. No. 003.
September 23, 2010.
Supreme Court, New York County.
DECISION AND ORDER
SHERRY KLEIN HEITLER, J.S.C.
In or about May 2008 plaintiff Shelly Bernard commenced this asbestos-related personal injury action against defendant THE OFFICE OF JAMES RUDERMAN, LLP ("Rudennan"), among others.[1].
Plaintiff was deposed on June 5, 2008. Among other things she claims that she was exposed to asbestos dust while working as a consultant for Salomon Brothers at 55 Water Street, a commercial office building in Manhattan (the "Building"). She worked at the Building from 1985 to approximately February 1988. While there plaintiff claims that renovations and construction were being performed where she worked on the 28th floor of the Building, which generated dust and debris to which she and her fellow workers were exposed for about a year. She testified there was dust all over her clothing and in her food, and described unfettered loose material hanging down like streamers which looked old, which she said was asbestos and insulation through which she had to wade to get to one part of the office from another. Plaintiff became sick in 2007 with ovarian cancer. She has been diagnosed with mesothelioma.
On August 11, 2008 plaintiff subsequently added COLGATE PALMOLIVE CORPORATION ("Colgate") as a defendant in this action, which answered the complaint against it and interposed cross claims against Ruderman and the other defendants. Defendant Ruderman is a structural engineering firm which was involved in construction activities at the Building during the relevant time periods. By Order to Show Cause dated August 26, 2009 (sequence 003) Ruderman again moves this court pursuant to CPLR 214-d, CPLR 3211(a)(7) and (h) and CPLR 3212(i) for summary judgment dismissing plaintiffs claims and all cross claims against it on the grounds that notices of claim pursuant to CPLR 214-d have not been properly filed or served upon it by any party and have not been properly pleaded in any complaint or cross claims asserted against it. Ruderman further contends it has no record of any work done by it on the 28th floor of the Building and therefore had no connection with the work site and exposure complained of by plaintiff, that it had no responsibility for any asbestos removal work being done at the Building, and that all of its plans and specifications for any work it did in the Building during the relevant time period specifically call for non-asbestos fireproofing. Ruderman asserts plaintiff had no basis upon which to claim there was asbestos in her workplace. Consequently Ruderman claims there is no ground upon which it may be held liable in this action. Ruderman thus asks the court to "so order" its No Opposition Summary Judgment Motion and Order, to which the plaintiff has consented, dismissing with prejudice the complaint and cross claims against it.
By Notice of Cross Motion dated October 7, 2009 defendant Colgate cross-moves for an order deeming Colgate's CPLR 214-d notice of claim addressed to Ruderman, dated October 1, 2009, which is annexed to Colgate's cross-motion papers as Exhibit A, to have been timely served nunc pro tunc[2] pursuant to CPLR 214-d(5), CPLR 3211(h), and CPLR 3212(i) on the ground there exists a substantial basis in law and fact for opposing Ruderman's dismissal motion. In this regard Colgate argues that Ruderman admits that it performed substantial work in the Building during the time plaintiff was there; it does not deny that it worked on the 28th floor at that time but merely asserts that it is unable to locate any record of having worked on the 28th floor; and that its plans for other floors at the time approved the use of vermiculite as a suitable fireproofing material in the Building, which Colgate urges has been found in other cases to be a carrier of asbestos and which fact Colgate asserts is confirmed by the United States Environmental Protection Agency's warning that the majority of vermiculite used in the United States from 1919 to 1990 was contaminated with asbestos (see, http;/www.epa.Gov/asbestos/pubs/yerm.html
Last undated June 7, 2010]) Colgate further points to Ruderman's involvement with the Building as the structural engineer on the project when the Building was initially constructed using asbestos-containing materials. Colgate asserts that it is entitled to the discovery afforded by CPLR 214-d to determine the nature of Ruderman's involvement in the selection and use of asbestos containing materials when the Building was constructed. Further Colgate seeks an order staying the within action pursuant to CPLR 214-d(5) until the motion and the cross motion are determined by the court.
In opposition to the cross motion Ruderman asserts that Colgate failed to file its notice of claim in accordance with the mandate of CPLR 214-d(5) and dismissal is therefore required. Ruderman further contends that Colgate has failed to show a substantial basis in law upon which to defeat its summary judgment motion in so far as Colgate provides no expert witness affidavit as to whether the use of vermiculite was outside the standards of competent practice in the 1980's when vermiculite was commonly used as a practice in the industry for fireproofing of structural members. Ruderman does not deny its involvement with the Building when it was initially constructed.
Plaintiff has put in no opposition to either the motion or the cross motion.
There is no evidence that Ruderman has joined issue by either serving an answer to plaintiffs complaint or to defendant Colgate's cross claim. Its CPLR 3212(i) summary judgment application is therefore denied as premature. However, Ruderman's pre-answer CPLR 3211(a)(7) and (h)[3] dismissal motion is viable. To the extent Ruderman seeks dismissal on the ground that both plaintiff and Colgate have failed to comply with the procedural requirements of CPLR. 214-d (i.e., service upon Ruderman of a notice of claim at least 90 days prior to commencement of an action against it, and inclusion in the subsequent pleading of the representation that there has been full compliance with the statute), Ruderman's motion is granted..
There is no dispute in this case that Ruderman falls within the protection of CPLR 214-d. "A plain reading of CPLR 214-d requires the Court to grant summary judgment dismissing any action where the parties have not complied with the requirements of this statute." Kretschmann v Board of Education of the Corning Painted Post School District, 184 Misc.2d 535, 537 (Sup. Ct. Steuben Co. 2000). CPLR 3211(h) similarly contains mandatory language to such effect. The court is mindful, however, that "compliance with CPLR 214-d(l) is not a jurisdictional prerequisite to commencing an action; rather, compliance with that statute is a condition precedent to commencement of an action, and such compliance must be pleaded in an action for personal injuries against a [licensed professional]. Thus, [a claimant's] initial failure to comply with that statute [does] not render the first action jurisdictionally defective, and a second action [may be] properly commenced pursuant to CPLR 205(a)." Kretschmann v. Board of Education of Corning Painted Post School District, 294 AD2d 39, 41-42 (4th Dept 2002). Neither plaintiff nor Colgate have disputed that each failed to serve a CPLR 214-d notice of claim upon Ruderman 90 days prior to serving their respective action/cross claim against Ruderman, nor does plaintiff dispute that its initial and amended pleadings do not contain the required representation that there has been full compliance with the notice of claim statute. What is also not in dispute, however, is that both plaintiffs and defendant Colgate's actions against Ruderman were not barred by the statute of limitations in the first instance. In this regard, CPLR 205 provides in relevant part:
(a) New action by plaintiff. If an action is timely commenced and is terminated in any other manner than by a voluntary discontinuance, a failure to obtain personal jurisdiction over the defendant, a dismissal of the
complaint for neglect to prosecute the action, or a final judgment upon the merits, the plaintiff, or, if the plaintiff dies, and the cause of action survives, his or her executor or administrator, may commence a new
action upon the same transaction or occurrence or series of transactions or occurrences within six months
after the termination provided that the new action would have been timely commenced at the time of
commencement of the prior action and that service upon defendant is effected within such six-month
period....
Thus it is not fatal if an an action or a cross claim is dismissed for non compliance with the notice of claim provision of CPLR 214-d; it can be saved if the claimant thereafter serves a notice of claim and after 90 days recommences an appropriate action within the six-month grace period of CPLR 205(a). (See, Kretschmann v Board of Education, supra, 294 AD2d 39; Alexander, 2001 Practice Commentaries, McKinney's Cons Laws of NY, Book 7B, C205:6 at 476.) The court believes it is necessary to here point out, in respect of Ruderman's "untimeliness" argument in opposition to Colgate's application to assert its notice of claim at this time, that nothing in CPLR 214-d provides for a 90-day window within which Colgate must have filed a notice of claim against Ruderman once it was brought into this action or once it became aware of Ruderman's first motion against plaintiff on the subject. Rather, the law provides that once Colgate does file its notice of claim it must
then wait ninety days before commencing an action or a cross claim against Ruderman. It may, however, conduct discovery within such time period. (See, CPLR 214-d[1], [4] and [5]). The relevant time period in terms of a matter in which CPLR 214-d applies obviously is whether or not the contemplated action or cross claim is timely in the first place. See CPLR 214-d(3). [4] Accordingly, Ruderman's CPLR 3211(a)(7) and (h) motion to dismiss the action and cross claims against it is granted without prejudice to the recommencement of an appropriate action or cross claim in compliance with the requirements of CPLR 214-d and CPLR 205. In this regard, the court declines at this time, and pending further proceedings herein, to "so order" Ruderman's No Opposition Summary Judgment Motion and Order.
To the extent Colgate seeks a stay pursuant to CPLR 214-d(5), its cross motion is denied as academic. CPLR 214-d, which operates in conjunction with CPLR 3211(h) and 3212(i), provides that an action shall automatically be stayed pending the outcome of any motion brought pursuant to CPLR 3211(h) or 3212(i). Likewise, Colgate's application for an order deeming its notice of claim, annexed to its papers as Exhibit A, to have been timely served nunc pro tunc is denied. As set forth above, the language of both CPLR 214-d(5) and CPLR 3211(h) is mandatory that an action shall be dismissed upon showing that the claimant has failed to comply with the notice of claim requirements of CPLR 214-d.
Further, Colgate has not on this motion met the heightened requirement of the "substantial basis" test of CPLR 3211(h). In Castle Village Owners Corp. v Greater New York Mut. Ins. Co., 58 AD3d 178, 183 (1st Dept 2008), the court defined the "substantial basis" test:
The `substantial basis' standard set forth in CPLR 3211(h) constitutes a departure from the standard
ordinarily applicable to the review of CPLR 3211 motions to dismiss for failure to state a cause of action.
Rather than determine whether the allegations of the complaint when viewed most favorably to the plaintiff
fall within any cognizable legal theory..., a court reviewing the sufficiency of a complaint under CPLR 3211(h) must look beyond the face of the pleadings to determine whether the claim alleged is supported by 'such
relevant proof as a reasonable mind may accept as adequate to support a conclusion or ultimate fact'....
While under this standard a plaintiff need not demonstrate that the claim is supported by a preponderance of
the evidence..., `a fair inference to be drawn from the legislative history is that CPLR 3211 (h) was intended to heighten the court's scrutiny of the complaint and thereby make it easier to dismiss a CPLR 214-d action
than other types of negligence actions'(Alexander, Practice Commentaries, McKinney's Cons Laws of NY,
Book 7B, CPLR 214-d, at 460). (Citations omitted.)
In Castle Village Owners Corp., supra, the First Department found the heightened requirement of CPLR 3211(h) had been satisfied where the complaint alleged with specificity and in detail that the defendant had departed from the professional standard of care and that its conduct was a proximate cause of the injury complained of, which allegations were supported by the affidavit of complainant's expert, a registered professional engineer. In denying the CPLR 3211(h) motion to dismiss the First Department determined, "[t]he allegations of the complaint and the expert affidavit provide a `substantial basis' to believe that [defendant] was negligent in the performance of its professional design duties and that the negligence was a proximate cause of the damage (Castle Village Owners Corp., supra, 58 AD3d at 184).
Here Colgate has failed to provide an appropriate expert's affidavit that Ruderman was negligent in the performance of its duties in permitting certain materials to be used in the Building which would be a proximate cause of plaintiffs exposure to asbestos in the Building. Accordingly, Colgate's request that the court accept its notice of claim annexed to its moving papers as served on Ruderman nunc pro tunc because there exists a substantial basis in law to assert Ruderman's negligence is also declined.
Accordingly, it is hereby
ORDERED that pursuant to CPLR 3211 (a)(7) and (h) the motion by The Office of James Ruderman, LLP to dismiss this action and all cross claims asserted against it is granted, without prejudice to recommencement of an appropriate action or cross claim in compliance with the provisions and requirements of CPLR 214-d and CPLR 205; and it is further
ORDERED, that the notice of claim annexed to Colgate's motion papers as Exhibit A shall be deemed served upon Ruderman upon service of a copy of this order with notice of entry; and it is further
ORDERED, that any and all other applications not specifically granted herein are denied.
This constitutes the decision and order of the court.
[1] In response to that summons and complaint, Ruderman moved this court in July of 2008 (sequence 001) for an order dismissing the action against it pursuant to CPLR 214-d, CPLR 3211(a)(7) and (h) and CPLR 3212 (i), invoking the 10-year notice of claim rule of CPLR 214-d. That motion was permitted to be withdrawn pursuant to this court's order entered on June 23, 2009. CPLR 214-d provides in relevant part:
- Any person asserting a claim for personal injury, wrongful death or property damage, or a cross or third-party claim for contribution or indemnification arising out of an action for personal injury, wrongful death or property damage, against a licensed...professional corporation or limited liability company lawfully practicing...engmeering...which is based upon the professional performance, conduct or omission by such...firm occurring more than ten years prior to the date of such claim, shall give written notice of such claim to each such...firm at least ninety days before the commencement of any action or proceeding against such...firm including any cross or third-party action or claim.**** CPLR 214-d(2) requires the inclusion in any subsequent pleading brought against such licensed professional the representation that there has been full compliance with this statute.
[2] On February 11, 2010 Colgate amended the cross-claims asserted by it against Ruderman in its Answer to include representations that it had fully complied with the requirements of CPLR 214-d.
[3] CPLR 3211(h) provides in relevant part: "Standards for motions to dismiss in certain cases involving licensed...engineers.... A motion to dismiss based on paragraph seven of subdivision (a) of this rule, in which the moving party has demonstrated that the action, claim, cross claim or counter-claim subject to the motion is an action in which a notice of claim must be served on a licensed...engineer....pursuant to the provisions of subdivision one of section two hundred fourteen of this chapter, shall be granted unless the party responding to the motion demonstrates that a substantial basis in law exists to believe that the performance, conduct or omission complained of such licensed...engineer...was negligent and that such performance, conduct or omission was a proximate cause of personal injury, wrongful death or property damage complained of by the claimant or is supported by a substantial argument for an extension, modification or reversal of existing law. The court shall grant a preference in the hearing of such motion. (Emphasis added.) [4] CPLR 214-d(3) provides: "Service of a notice as provided in this section shall toll the applicable statute of limitations to and including a period of one hundred twenty days following such service."
Sources
How to cite it
Cite the decision
Bernard v. Brookfield Prop. Corp., 2010 NY Slip Op 32666(U) (New York Supreme Court September 23, 2010).
Cite our summary
“Summary of Bernard v. Brookfield Prop. Corp.” AsbestosClaims.Law Library. https://asbestosclaims.law/library/cases/bernard-v-brookfield-prop-corp-2010-09-23.
ACL Doc numbers and their short links never change. See how to cite the Library.
Talk with an asbestos lawyer
Start with what you remember, and we'll take it from there.
This page is provided for general informational purposes and does not constitute legal advice. Every asbestos case turns on its own facts, exposure history, diagnosis, deadlines, available evidence, and applicable law. Reviewing this page does not create an attorney-client relationship. For advice about your specific situation, call 833-4-ASBESTOS for a free case review.