4 results for “Union Carbide Corporation”
-
Company document · Union Carbide documents · December 15, 1983
Union Carbide Sistersville Plant Capital Work Order 380-564, Safety & Health – Insulation (Asbestos Insulation Replacement), with Handwritten Notes (1983)
Capital work order package for a $500,000 project to repair or replace exposed asbestos insulation in the Steam Plant and Monomers Area of the Sistersville, WV plant, replacing it with calcium silicate insulation. It includes the work order form, an…
-
Company document · Union Carbide documents · September 1986
Removals & Retirements Work Order 838-2391: Asbestos Insulation Control, Upper Island Chemical Complex, South Charleston Plant (1986)
A capital work order (Removals & Retirements, job NP-2147, request 514-0544) authorizing $26,000 to remove asbestos insulation from idle equipment and lines in the Upper Island DAA/MSO facilities and unused Ethanol DSP facilities at the South…
-
Company document · Union Carbide documents · December 9, 1986
J. F. Dodd Transmittal of Work Order Request for Asbestos Insulation Removal at the Oxide Adducts Unit, South Charleston Plant (1986)
A December 9, 1986 transmittal memo forwards an approved Work Order Request (514-0560) for removing and replacing asbestos insulation in the Oxide Adducts Unit at the South Charleston Plant. The attached three-page work order gives a total estimate…
-
Company document · Union Carbide documents · May 28, 1987
J. F. Dodd to W. D. Bradbury, Jr. and M. G. Dwyer transmitting Work Order Request 514-0586, Asbestos Insulation Upgrade Phase I, South Charleston Plant (1987)
A cover memo transmits a locally approved capital work order request for a $900,000 capital and $270,000 expense project to upgrade asbestos insulation at the South Charleston Plant. The attached 8-page request gives the justification as…