16 results for “Union Carbide Corporation”
-
Company document · Union Carbide documents · November 22, 1985
G. W. Phares to B. H. Avashia, M.D., and Others on Asbestos Monitoring at South Charleston Plant (1985)
Internal Union Carbide memo reporting asbestos exposure monitoring done on November 18, 1985 while construction employees stripped and bagged insulation from a tank at the South Charleston polyols unit. It states that all samples were below…
-
Company document · Union Carbide documents · June 20, 1984
M. A. Patel to J. W. Karn on Asbestos Monitoring at the Sistersville Plant (1984)
Memo from M. A. Patel to J. W. Karn transmitting results of asbestos air monitoring at the Sistersville Plant (Steam Plant third level and Polymer 2, Building 48) during insulation stripping on April 2 and 25, 1984. It reports high fiber levels in…
-
Company document · Union Carbide documents · December 12, 1984
M. F. Stowers to G. W. Phares on Asbestos Monitoring During Insulation Stripping at the Institute Plant (1984)
Internal memo reporting personal asbestos exposure monitoring on November 13, 1984 during stripping of about 100 ft of asbestos-containing steam line insulation at the Institute plant. It states that all four samples were well below the 2.0 fibers…
-
Company document · Union Carbide documents · July 17, 1981
Industrial Hygiene Monitoring for Asbestos: R. F. Painter Report on Insulation Stripping and Bagging, Bldg. 774 (1981)
Four 'Industrial Hygiene Monitoring for Asbestos' forms (Computer Ref. W-1198), dated July 17, 1981 and stamped Business Confidential. They report AM and PM personal air samples for four workers on 07/10/81 during stripping and bagging of insulation…
-
Company document · Union Carbide documents · July 16, 1982
Manhar A. Patel to J. C. Smith on Dust and MEK Monitoring in the Sandblast Shed, 511 Construction Institute Plant (1982)
Internal Union Carbide letter reporting dust sampling for 'Black Beauty' in the Sandblast Shed and methyl ethyl ketone (MEK) sampling in the Paint Preparation Shed at the 511 Construction Institute Plant, May-June 1982. It says…
-
Company document · Union Carbide documents · June 20, 1984
M. A. Patel to J. W. Karn on Asbestos Monitoring at the Sistersville Plant (1984)
Memorandum from M. A. Patel to J. W. Karn transmitting results of asbestos air monitoring at the Sistersville Plant (Steam Plant and Polymer 2, Building 48) during insulation stripping by Construction Department employees on April 2 and 25, 1984.…
-
Company document · Union Carbide documents · May 16, 1985
M. F. Stowers to R. S. Howell on Asbestos Monitoring During Insulation Stripping at the Institute Plant (1985)
Internal memo reporting asbestos air monitoring done on May 7, 1985 while construction employees stripped about 200 ft. of insulation from 3 inch process lines near the Pesticide B Unit at the Institute plant. It states all samples were below the…
-
Company document · Union Carbide documents · June 20, 1984
M. A. Patel to J. W. Karn on Asbestos Monitoring at Sistersville Plant (1984)
Memorandum from M. A. Patel to J. W. Karn transmitting results of asbestos exposure monitoring at the Sistersville Plant (Steam Plant and Polymer 2, Building 48) during insulation stripping on April 2 and 25, 1984. The memo states that Building 48…
-
Company document · Union Carbide documents · October 20, 1981
M. A. Patel to W. L. Browning and J. W. Perry, Jr. on Asbestos Monitoring in the Gasket Shop, Institute Plant (1981)
Internal memo reporting area and personal asbestos exposure monitoring in the Gasket Shop (laundry, Building 3 of the Construction Department) at the Institute Plant, done by the plant's industrial hygiene group on October 2 and 9, 1981. It states…
-
Company document · Union Carbide documents · November 13, 1987
M. A. Patel to P. L. Graham et al. on Respiratory Protection for Asbestos, with 1984 R. G. Hanlon Memo and DuPont Respirator Study Figures (1987)
A November 13, 1987 internal memo from Manhar A. Patel forwarded a DuPont study of respirator performance against asbestos fibers and continued to recommend 3M respirators. Attached were a November 6, 1984 Richard G. Hanlon memo on the same subject,…
-
Company document · Union Carbide documents · November 22, 1983
Manhar A. Patel to D. R. Paugh Transmitting the 1984 Industrial Hygiene Program for the 511 Construction Department (1983)
Internal Union Carbide correspondence from Manhar A. Patel transmitting a 1984 industrial hygiene program for the 511 Construction Department. The attached program lists planned exposure monitoring by shop and frequency, including dust in the insulation shop…
-
Company document · Union Carbide documents · October 23, 1981
M. A. Patel to W. L. Browning, J. W. Perry Jr. and Others on Asbestos Monitoring in the Gasket Shop, 512 Construction, Institute Plant, with Replacement Letter and Data Sheet (1981)
Internal Union Carbide correspondence from Manhar A. Patel. A cover note says an October 20, 1981 letter on asbestos monitoring in the Institute Plant gasket shop contained an error and should be replaced. The replacement letter…
-
Company document · Union Carbide documents · January 19, 1984
M. A. Patel to M. L. Mills on Identification of an Unknown Material at the Institute Plant, with L. D'Esposito's IR Spectrum Memo (1984)
Internal Union Carbide correspondence from January 1984 about a white powdery material found oozing from the floor of the field toilet in the construction shop area at the Institute plant. An R/D memo reported an…
-
Company document · Union Carbide documents · February 1, 1984
M. A. Patel to J. W. Karn on Asbestos Monitoring of Construction Employees at the Sistersville Plant (1984)
Memo reporting personal exposure monitoring for asbestos on January 12, 1984, while Construction Department employees stripped asbestos-containing pipe insulation at the Sistersville Plant steam plant. It states all monitored results were below the…
-
Company document · Union Carbide documents · June 21, 1983
Manhar A. Patel to R. C. Proffitt on Asbestos Monitoring in the Storeroom, 511 Construction Department (1983)
Internal Union Carbide correspondence reporting a May 9, 1983 industrial hygiene monitoring survey of asbestos dust exposure while an employee handled asbestos spiral-wound gaskets in the 512 Construction Department storeroom. It reports that exposure above…
-
Company document · Union Carbide documents · April 12, 1985
G. W. Phares to B. H. Avashia and Others on Asbestos Monitoring at the Institute Plant SEVIN Unit (1985)
Internal Union Carbide memo reporting asbestos exposure monitoring on April 9, 1985, when two construction insulators stripped about 20 ft. of old insulation from a 6 inch steam line at the SEVIN unit at the Institute…