Company document · Union Carbide documents · July 1, 1997
Union Carbide Texas City Plant Notice of Intention to Demolish or Renovate B-94 Ethanol Unit Containing Asbestos, Completed by Mickey Gill (1997)
A one-page handwritten-entry form, page 1 of 3 of a Texas City Plant asbestos subject form, giving notice of intent to remove asbestos-containing material from the B-94 Ethanol Unit. It lists an estimated 11,000 sq. ft. of asbestos material, about…
-
Company document · Union Carbide documents · February 2, 1996
Union Carbide Texas City Plant Notice of Intention to Demolish or Renovate a Structure Containing Asbestos Material, Building #21 (1996)
A partly handwritten Union Carbide Texas City Plant form giving notice of planned asbestos removal in Building #21. It lists about 1500 linear feet of material, Thorpe Insulation Services as contractor, abatement dates, and the removal…
-
Company document · Union Carbide documents · April 23, 1992
Texas City Plant Notice of Intention to Renovate a Facility Containing Asbestos Material, B-219 Ethylene Oxide Rack (1992)
A one-page Texas City Plant form (Plant Procedure SH-5.6, Attachment #1) giving notice of intent to renovate a facility containing asbestos material. The handwritten entries describe the B-219 EC header at the ethylene oxide rack, less than 4 sq ft…
-
Company document · Union Carbide documents · June 9, 1993
C. Eric Kaibley, Notice of Intention to Renovate Asbestos-Insulated Pipe at Texas City Plant, Building 94 (1993)
A handwritten-in form (Plant Procedure SH-5.6, Attachment #1) giving notice of intent to remove asbestos insulation from about 30 linear feet of an 8-inch secondary condensate tank tails suction line at B94, Texas City Plant. The form lists UCC as…
-
Company document · Union Carbide documents · July 7, 1991
Notice of Intention to Demolish or Renovate a Structure Containing Asbestos Material, DHC Jet Condenser, Texas City Plant, completed by W. F. Lanigan (1991)
A Texas City Plant form (Plant Procedure SH-5.6, Attachment #1) giving notice of intent to remove a DHC jet condenser in Bldg. 16 containing asbestos material. The handwritten entries give a 1.7 sq ft estimate, a 20-year age, removal by UCC on…
-
Company document · Union Carbide documents · July 15, 1991
Notice of Intention to Demolish or Renovate a Structure Containing Asbestos Material, Acetylene Still Water Condenser, Texas City Plant (1991)
A completed Texas City Plant form (Plant Procedure SH-5.6, Attachment #1) giving notice of a planned removal of asbestos insulation from an acetylene still water condenser. According to the handwritten entries, the work covered about 400 sq. ft. of…
-
Company document · Union Carbide documents · July 7, 1991
W. F. Lanigan Notice of Intention to Renovate Asbestos-Containing Structure, GSC Jet Condenser, Texas City Plant (1991)
A Texas City Plant form (Plant Procedure SH-5.6, Attachment #1) giving notice of intent to remove asbestos-containing material from a GSC jet condenser in Building 16. Handwritten entries give 27 sq ft of material, an estimated age of 20 years,…
-
Company document · Union Carbide documents · July 15, 1991
Notice of Intention to Demolish or Renovate a Structure Containing Asbestos Material, Deethanizer Column, Texas City Plant, completed by Vikki Robbins (1991)
A handwritten-in company form (Plant Procedure SH-5.6, Attachment #1) giving notice of planned removal of asbestos insulation from a deethanizer column in No. 3 Olefins, Bldg. 238, at the Texas City Plant. It lists about 550 sq. ft. of material,…
-
Company document · Union Carbide documents · March 22, 1993
Notice of Intention to Renovate Asbestos Insulation on a Steam Line at the FARM Unit, Texas City Plant, completed by A. L. Welch (1993)
Completed Texas City Plant form (Plant Procedure SH-5.6, Attachment #1) giving notice of intent to renovate a structure containing asbestos material. It describes removal of 6 linear feet of asbestos insulation on a 200 # steam line at the FARM unit…
-
Company document · Union Carbide documents · December 9, 1993
Notice of Intention to Demolish or Renovate a Structure Containing Asbestos Material, #19 Furnace at No. 3 Olefins, Texas City Plant, completed by Al Jivan (1993)
A handwritten-in plant form (Plant Procedure SH-5, Attachment #1) giving notice of planned removal of old asbestos-containing insulation from piping north of #19 Furnace at No. 3 Olefins, Texas City. It lists about 10 linear feet of material,…
-
Company document · Union Carbide documents · July 10, 1992
J. D. Washington Notice of Intention to Renovate Asbestos-Containing Pipe at Texas City Plant (1992)
…Bldg 124, about 8 feet of asbestos-containing material, 24 years old, to be removed by Union Carbide on 7/11/92. A handwritten note says the industrial supervisor was notified by telephone before the notice.