Company document · Union Carbide documents · September 24, 1987
Union Carbide Petrochemical Divisions Safety and Health Information Manual No. 46, Assigned to J. R. Dement, with Internal Exposure Standards List (1987)
…September 24, 1987, restricted for internal use only Union Carbide Internal Exposure Standards List (pages 1-18 of the list, alternating with pages of notes of explanation and definitions), including the asbestos entry on page 3…
-
Company document · Union Carbide documents · 1987
Union Carbide Asbestos Removal and Phase-Out Papers, Including T. E. Hanning Memo on Contractor Project Development Group (1987)
…Chemicals and Plastics Business Group, use of asbestos-containing materials in the work place Grafoil seminar outline and cover sheet (Union Carbide Specialty Products Group, Cleveland) Grafoil flexible graphite newsletter on special gasketing techniques Distribution list…
-
Company document · Union Carbide documents · May 1987
Union Carbide Memos and Draft C&P Program on Phasing Out Asbestos-Containing Materials in Company Workplaces (1986-1987)
Six pages of Union Carbide papers from 1986-1987 on asbestos in the company's own facilities. They include a 9/29/86 draft Chemicals and Plastics (C&P) program to phase out asbestos-containing materials…
-
Company document · Union Carbide documents
Handwritten Asbestos Abatement Project Meeting Notes and J. R. Dement Note to J. C. Wandell on Maintenance Procedure
Page 1 is an unsigned handwritten set of notes headed 'Asb Abatement Project Mtg', listing agenda items and five steps for an asbestos insulation project, including pre-approval of funds and allocation factors. Page 2 is a handwritten note from J.…
-
Company document · Union Carbide documents · March 25, 1987
J. K. Corrie to Maintenance Staff Transmitting Draft Maintenance Safety Procedure XVIII, Asbestos Handling, South Charleston Plant (1987)
A March 25, 1987 cover memo from J. K. Corrie circulating a final review draft of Maintenance Safety Procedure XVIII, Asbestos Handling, for the South Charleston plant, with comments requested by April 3, 1987. The attached 20-page draft (dated…
-
Company document · Union Carbide documents · May 21, 1987
South Charleston Plant Accident/Incident Report and Review Board Analysis on Vapor Release Under Plastic Enclosure at Tanks 643-644 During Asbestos Insulation Removal (1987)
Accident/incident report and informal Review Board analysis of a May 21, 1987 near-miss in the Polyols department at South Charleston. Reactor contents transferred to tank 643 vented into a plastic enclosure installed for asbestos insulation…
-
Company document · Union Carbide documents · September 2, 1987
L. S. Magelssen and H. W. Wegert to J. F. Dodd et al. on Status of Contingency Items for Asbestos Insulation Removal Upgrade, South Charleston (1987)
Two-page memorandum reporting that two contingency items attached to the May 19, 1987 health, safety and environmental endorsement of the South Charleston Asbestos Insulation Removal Upgrade-Phase I had been resolved. It discusses review of the…
-
Company document · Union Carbide documents · June 11, 1987
M. J. Shoger to J. K. Corrie and Others on Asbestos Enclosures and HWP Requirements Meeting (1987)
Internal Union Carbide memo announcing a June 19 meeting, sponsored by Chuck Rotthoff, with Institute, South Charleston and Sistersville personnel on plant practices for enclosures used in asbestos removal. It states there were two close calls…
-
Company document · Union Carbide documents · February 11, 1987
W. J. Vincent to J. K. Corrie Transmitting Responses to Asbestos Abatement and Removal Questions, South Charleston Plant (1987)
Internal Union Carbide memo from W. J. Vincent to J. K. Corrie forwarding answers to questions raised at a recent meeting on asbestos abatement and removal. The attached "Asbestos Management" Q&A covers negative pressure enclosures…
-
Company document · Union Carbide documents · July 7, 1987
J. K. Corrie to H. W. Wegert and G. M. Whipple on Environmental Concerns in the South Charleston Insulation Upgrade Project, with Revised Asbestos Handling Procedure (1987)
Internal correspondence from J. K. Corrie transmitting the revised South Charleston Plant Maintenance Safety Procedure XVIII on asbestos handling. The memo says the revision addresses concerns raised in an October 30, 1986 review of the plant's…
-
Company document · Union Carbide documents · October 30, 1986
H. W. Wegert and G. M. Whipple to J. R. Dement et al. on Health, Safety, and Environmental Review of the South Charleston Insulation Upgrade Project (1986)
Memorandum reporting a health, safety and environmental review of a three-year project to upgrade asbestos insulation at the South Charleston Plant. It recommended endorsement contingent on revising Maintenance Procedure XVIII to comply with the…
-
Company document · Union Carbide documents · March 4, 1986
D. H. Ott to J. R. Dement and S. Rossi on Tank Insulation in 1986, with Tank Insulation Needs Table (1986)
A March 4, 1986 memo from D. H. Ott to J. R. Dement and S. Rossi about the 1986 budget for tank insulation and weatherproofing work in Polyols, noting two tanks were started in 1985 because of the need to remove damaged asbestos insulation. The…
-
Company document · Union Carbide documents · February 24, 1987
W. J. Vincent to All Department Heads on Labelling of Asbestos Materials, with Standard Practice SH-256 on Removal and Handling of Asbestos-Containing Insulation (1987)
A February 1987 internal memo from the South Charleston Plant Safety and Health Department told department heads that asbestos warning labels were now required on installed asbestos products whenever feasible and gave the supplier and cost. Attached…
-
Company document · Union Carbide documents · July 22, 1987
S. B. Kovach to D. R. Stokely Transmitting SHARE Inspection Results, South Charleston Plant (1987)
Cover letter from the South Charleston Plant SHARE Coordinator sending D. R. Stokely the findings of a SHARE inspection held July 22, 1987, and setting program goals for correcting deficiencies. It has a 30/60/90-day progress update block and…
-
Company document · Union Carbide documents · July 6, 1987
Memo to J. R. Soice on Alternate Asbestos Disposal Site Bids, South Charleston Plant (1987)
Internal memo summarizing responses to solicitations of bids from seven companies for asbestos disposal. It lists the Browning-Ferris (Marietta, Ohio), E.R.O. Landfill and Don's Disposal (Craigs Branch Landfill) sites, with prices and permit status,…
-
Company document · Union Carbide documents · February 11, 1987
W. J. Vincent to J. K. Corrie Transmitting Responses to Asbestos Abatement Questions, South Charleston Plant (1987)
Internal Union Carbide memo from W. J. Vincent to J. K. Corrie, stamped received by the Maintenance Department on Feb. 17, 1987, forwarding answers to questions on asbestos raised at a recent meeting on asbestos abatement…
-
Company document · Union Carbide documents · August 23, 1987
T. G. Huff to S. W. Drake and Others: Project Scope Document for B-303 Demolition and Transite Siding Removal, South Charleston Plant (1987)
Project scope document for demolishing part of Building 303 at the South Charleston Plant and replacing asbestos-containing transite siding on the Chemical Mixing Unit Slurry Bay with insulated metal panels. It sets out mechanical, electrical and…
-
Company document · Union Carbide documents · May 6, 1987
D. H. Hanshew to J. R. Dement on Environmental Concerns about the South Charleston Plant Insulation Upgrade Project and Asbestos Handling Procedure (1987)
Memo responding to a 10-30-86 memo from H. W. Wegert and G. M. Whipple about the Health, Safety, and Environmental Review of the South Charleston insulation upgrade project. It addresses three concerns about notification, disposal container labels…
-
Company document · Union Carbide documents · May 19, 1987
L. S. Magelssen and H. W. Wegert to J. R. Dement and Others on Health, Safety and Environmental Review of the South Charleston Asbestos Insulation Removal Upgrade, Phase I (1987)
A May 19, 1987 memo recommending endorsement of Phase I of a project to remove and upgrade asbestos insulation at the South Charleston plant. The endorsement is contingent on revising Maintenance Procedure XVIII to comply with OSHA 29 CFR 1926.58…
-
Company document · Union Carbide documents · January 9, 1987
C. R. Rotthoff to W. J. Vincent on South Charleston Provisions for Asbestos Material Removal and Disposal (1987)
Internal correspondence in which C. R. Rotthoff commented on W. J. Vincent's South Charleston asbestos removal document, saying it assumed no technology exists to keep asbestos below the PEL. He suggested identifying which steps are mandatory…