No fee unless we recover compensation for your family Text size 833-4-ASBESTOS (833-427-2378) Free Case Review

Search

28 results for “Union Carbide Corporation”, page 1 of 2

  1. Company document · Union Carbide documents · January 15, 1986

    Cathy Wells to B. R. McMakin and R. W. Scoular Forwarding Tom Collins' Asbestos Removal Letter and Attachment (1986)

    A short cover memo stating that the attachment to Tom Collins' January 8, 1986 letter regarding asbestos removal had been left out of the envelope. The letter was reprinted and enclosed with the attachment. The memo carries a Safety Dept. received…

  2. Company document · Union Carbide documents · September 15, 1987

    H. E. Rucker, Asbestos Exposure Monitoring at the Institute Plant Pipe Insulation Removal (1987)

    Internal Union Carbide memo transmitting results of personal air monitoring during removal of asbestos insulation from about 180 feet of 6-inch product line in a trench at the Institute Plant. It reports that four of…

  3. Company document · Union Carbide documents · October 6, 1986

    V. E. Stover and M. A. Patel to J. M. Harbert and Others on Asbestos Exposure Monitoring at South Charleston Building 309 (1986)

    Internal Union Carbide memo transmitting results of asbestos exposure monitoring of two employees on September 9, 1986 at the South Charleston plant's Building 309, while they stripped and bagged asbestos from a 1 inch line…

  4. Company document · Union Carbide documents · June 20, 1984

    M. A. Patel to J. W. Karn on Asbestos Monitoring at the Sistersville Plant (1984)

    Memo from M. A. Patel to J. W. Karn transmitting results of asbestos air monitoring at the Sistersville Plant (Steam Plant third level and Polymer 2, Building 48) during insulation stripping on April 2 and 25, 1984. It reports high fiber levels in…

  5. Company document · Union Carbide documents · December 12, 1984

    M. F. Stowers to G. W. Phares on Asbestos Monitoring During Insulation Stripping at the Institute Plant (1984)

    Internal memo reporting personal asbestos exposure monitoring on November 13, 1984 during stripping of about 100 ft of asbestos-containing steam line insulation at the Institute plant. It states that all four samples were well below the 2.0 fibers…

  6. Company document · Union Carbide documents · January 6, 1984

    L. R. Noble to J. W. Barna and Others on Asbestos Insulation Removal Project, Steam Plant and Monomers Unit, Sistersville Plant (1984)

    Memorandum documenting a January 5, 1984 meeting on how Construction Department employees would remove asbestos insulation from piping and equipment in the Monomers Unit and Steam Plant at the Sistersville Plant. It sets out eight action steps: EPA…

  7. Company document · Union Carbide documents · March 17, 1987

    Manhar A. Patel to B. R. McMakin on Asbestos Medical Surveillance and Preassignment Examinations (1987)

    Internal Union Carbide memo from Manhar A. Patel to B. R. McMakin about whether the company's plan of giving employees medical exams in their birthday month meets the preassignment medical surveillance requirements of the OSHA…

  8. Company document · Union Carbide documents · June 20, 1984

    M. A. Patel to J. W. Karn on Asbestos Monitoring at the Sistersville Plant (1984)

    Memorandum from M. A. Patel to J. W. Karn transmitting results of asbestos air monitoring at the Sistersville Plant (Steam Plant and Polymer 2, Building 48) during insulation stripping by Construction Department employees on April 2 and 25, 1984.…

  9. Company document · Union Carbide documents · January 8, 1986

    T. L. Collins to B. R. McMakin and R. W. Scoular on EPA Enforcement of Asbestos Removal Regulations (1986)

    Internal Union Carbide Technical Center memo transmitting an item from the January 3, 1986 issue of Inside EPA on enforcement of asbestos removal regulations. The memo said EPA was apparently giving high priority to monitoring asbestos…

  10. Company document · Union Carbide documents · May 16, 1985

    M. F. Stowers to R. S. Howell on Asbestos Monitoring During Insulation Stripping at the Institute Plant (1985)

    Internal memo reporting asbestos air monitoring done on May 7, 1985 while construction employees stripped about 200 ft. of insulation from 3 inch process lines near the Pesticide B Unit at the Institute plant. It states all samples were below the…

  11. Company document · Union Carbide documents · October 7, 1986

    R. W. Gilbert to B. H. Avashia, W. L. Browning and Others on Asbestos Exposure Monitoring in the Institute Construction Storeroom (1986)

    Internal Union Carbide memo reporting asbestos air monitoring done on August 19 and 26, 1986 in the Construction Storeroom, Building 2002, at Institute, while two employees dispensed asbestos gaskets. It describes the results, recommends HEPA vacuum…

  12. Company document · Union Carbide documents · January 6, 1984

    L. R. Noble to J. W. Barna and Others on the Asbestos Insulation Removal Project at the Sistersville Plant Steam Plant and Monomers Unit (1984)

    Memorandum documenting a January 5, 1984 meeting on how the Construction Department would remove asbestos insulation from piping and equipment in the Monomers Unit and Steam Plant at the Sistersville Plant. It lists eight action steps with…

  13. Company document · Union Carbide documents · January 21, 1987

    Manhar A. Patel to B. H. Avashia, M.D. and Others on Asbestos Respiratory and Medical Surveillance Requirements, with OSHA Standard Excerpts (1987)

    Internal Union Carbide memo from Manhar A. Patel transmitting the respiratory protection and medical surveillance requirements of the OSHA asbestos standard for asbestos abatement jobs. It discusses medical questionnaires, six-month respirator fit tests, training, and…

  14. Company document · Union Carbide documents · September 18, 1987

    Industrial Hygiene (EM&TS - HS&EA) to H. E. Rucker on Asbestos Exposure Monitoring During Pumphouse Pipe Stripping (1987)

    Internal Union Carbide memo transmitting results of asbestos air monitoring done during removal of asbestos insulation from about 310 feet of pipe at the #1 Pumphouse and about 50 square feet from a reactor at Building…

  15. Company document · Union Carbide documents · May 21, 1987

    M. A. Patel to B. R. McMakin and R. W. Scoular transmitting Draft Asbestos Containing Material Removal and Handling Procedure (1987)

    Internal Union Carbide Technical Center memo from Manhar A. Patel transmitting a draft procedure for removal and handling of asbestos-containing material and asking recipients to review it and adopt it in their department safety and…

  16. Company document · Union Carbide documents · June 20, 1984

    M. A. Patel to J. W. Karn on Asbestos Monitoring at Sistersville Plant (1984)

    Memorandum from M. A. Patel to J. W. Karn transmitting results of asbestos exposure monitoring at the Sistersville Plant (Steam Plant and Polymer 2, Building 48) during insulation stripping on April 2 and 25, 1984. The memo states that Building 48…

  17. Company document · Union Carbide documents · January 21, 1987

    Manhar A. Patel to B. H. Avashia, M.D., and Others on Asbestos Respiratory and Medical Surveillance Requirements, with OSHA Standard Excerpts (1987)

    A two-page Union Carbide internal memo of January 21, 1987, from Manhar A. Patel to medical, safety and engineering staff, forwarding the respirator and medical surveillance requirements of the OSHA asbestos standard for asbestos abatement…

  18. Company document · Union Carbide documents · April 16, 1986

    V. E. Stover to C. K. Campbell on Asbestos Testing of Pipe Insulation Near the Sandblasting Shop, Institute Plant (1986)

    Internal correspondence reporting that, at C. K. Campbell's request, insulation samples were collected from three pipelines near the Construction sandblasting shop at the Institute plant, where the insulation was reported to be crumbling. Two of the…

  19. Company document · Union Carbide documents · January 6, 1984

    L. R. Noble to Distribution on Asbestos Insulation Removal Project, Steam Plant and Monomers Unit, Sistersville Plant (1984)

    Memorandum documenting a January 5, 1984 meeting on precautions for Construction Department employees removing asbestos insulation from piping and equipment in the Monomers Unit and Steam Plant at the Sistersville Plant. It lists eight action items:…

  20. Company document · Union Carbide documents · July 23, 1987

    Industrial Hygiene to H. E. Rucker on Asbestos Exposure Monitoring During Pipe Insulation Removal at the Institute Plant (1987)

    Internal Union Carbide memo reporting asbestos air monitoring on insulators who stripped about 195 feet of 3-inch steam line at the Institute Plant tank farm. It states that all personal samples were below the 0…