69 results for “Union Carbide Corporation”, page 1 of 4
-
Company document · Union Carbide documents · 1980
Union Carbide Industrial Hygiene Monitoring for Asbestos Forms, Bldg. 777 Insulation Stripping, Including Reports to R. F. Painter (1980)
Seven "Industrial Hygiene Monitoring for Asbestos" forms dated February to September 1980, mostly for work in Bldg. 777. They record fiber concentrations, sampling times, time-weighted averages, the OSHA allowable exposure, and comments on wetting…
-
Company document · Union Carbide documents · August 25, 1980
Industrial Hygiene Monitoring for Asbestos: Insulation Stripping and Bagging at Bldg. 777, Addressed to R. F. Painter (1980)
Three Industrial Hygiene Monitoring for Asbestos forms (Computer Ref. W-1078) reporting air samples taken 8/25/80 at Bldg. 777, between the eastern side of the ACR unit and the dewatering shed, during insulation stripping and bagging. Each form…
-
Company document · Union Carbide documents · August 1980
Industrial Hygiene Monitoring Reports for Asbestos During Insulation Stripping in Bldg. 777, to R. F. Painter (1980)
Five 'Industrial Hygiene Monitoring for Asbestos' report forms covering workers wetting, bagging and stripping insulation in Bldg. 777. On 8/18/80 and 8/19/80, R. E. Templeton's samples gave time-weighted averages of 2.8 and 2.5 fibers >5 µm/cm3,…
-
Company document · Union Carbide documents · April 28, 1980
Industrial Hygiene Monitoring for Asbestos at #1 Powerhouse, Institute: Insulation Stripping and Bagging Results for Jividen, Cobb and Grant (1980)
Three industrial hygiene monitoring forms dated 4/28/80 report airborne asbestos fiber sampling at the #1 Powerhouse at Institute while insulation was stripped from steam lines on the #1 boiler and bagged for disposal. Sample results are given for…
-
Company document · Union Carbide documents · August 1980
Industrial Hygiene Monitoring for Asbestos: D. C. Shamblin Stripping Insulation, Bldg. 777, Reports to R. F. Painter (August 1980)
Two Industrial Hygiene Monitoring for Asbestos forms covering personal air sampling of D. C. Shamblin while stripping insulation in Bldg. 777, Room 111, on 8/18/80 and 8/19/80. The forms list fiber concentrations, time-weighted averages compared…
-
Company document · Union Carbide documents · September 12, 1980
G. F. Hurley to L. R. Noble, H. L. Robinson, E. C. Shipley and F. Williams on Asbestos Exposure Monitoring in the SEVIN Operations Area (1980)
Letter-style memo reporting asbestos air monitoring in the SEVIN operations area on September 3, 1980, which showed 0.1 fiber per cc, described as well below the OSHA standard. Six breathing-zone samples were taken on three men, but only one valid…
-
Company document · Union Carbide documents · July 17, 1981
Industrial Hygiene Monitoring for Asbestos: Insulation Stripping and Bagging Samples, Bldg. 774, Report to R. F. Painter (1981)
Four Union Carbide industrial hygiene monitoring forms (Computer Ref. W-1198), dated July 17, 1981, reporting airborne asbestos fiber results for four workers sampled on 07/10/81 while stripping and bagging insulation from a steam…
-
Company document · Union Carbide documents · August 5, 1980
Industrial Hygiene Monitoring for Asbestos: Air Samples for J. W. Greenlee and R. E. Raines, Building 707 (1980)
Two Industrial Hygiene Monitoring for Asbestos forms dated 8/5/80, each reporting one air sample taken in Bldg. 707, Fourth Level, Cell 11, during stripping and bagging of suspected asbestos-containing insulation from about 50 feet of steam line.…
-
Company document · Union Carbide documents · April 22, 1981
Industrial Hygiene Monitoring for Asbestos: Insulator Pipe Stripping at Bldg. 773 Tank Pad, J. F. Chandler and D. C. Shamblin, to R. F. Painter (1981)
Two Union Carbide industrial hygiene monitoring forms for asbestos, dated 04/22/81, reporting air sampling on 04/20/81 of two insulators stripping about 100 feet of 1-1/2" pipe insulation outside Bldg. 773…
-
Company document · Union Carbide documents · August 19, 1980
Industrial Hygiene Monitoring for Asbestos Reports to W. T. Shelton on Insulation Stripping in Bldg. 706 (1980)
Two industrial hygiene monitoring forms for asbestos dated 8/19/80, each reporting one air sample taken in Bldg. 706 (West End, second and third level) while a worker stripped and bagged insulation on the G-101 autoclave and adjacent lines. The…
-
Company document · Union Carbide documents · September 12, 1980
G. F. Hurley to B. E. Bess and Others on Asbestos Exposure Monitoring in the SEVIN Operations Area (1980)
Letter reporting asbestos air monitoring in the SEVIN operations area on September 3, 1980, which showed 0.1 fiber per cc. Six breathing-zone samples were taken on three men, but an analytical error left only one valid sample, for Mr. Smith. The…
-
Company document · Union Carbide documents · September 12, 1980
G. F. Hurley to B. E. Bess, P. W. Young and Others on Asbestos Exposure Monitoring in the SEVIN Operations Area (1980)
Letter reporting that asbestos monitoring in the SEVIN operations area on September 3, 1980 showed 0.1 fiber per cc, which it described as below the present OSHA standard. Six breathing-zone samples were taken on three men, but because of an…
-
Company document · Union Carbide documents · September 12, 1980
G. F. Hurley to B. E. Bess and Others on Asbestos Exposure Monitoring in the SEVIN Operations Area (1980)
Letter-style memo dated September 12, 1980, reporting asbestos air monitoring in the SEVIN operations area on September 3, 1980, which showed 0.1 fiber per cc. It states that six breathing-zone samples were taken on three men, but only one valid…
-
Company document · Union Carbide documents · March 19, 1982
Industrial Hygiene Monitoring for Asbestos, Building 701-100 Insulation Cleanup, Reported to J. E. Midkiff (1982)
Four pages of Union Carbide industrial hygiene monitoring reports (computer refs. W-1401, W-1402, W-1405) dated March 19, 1982, giving airborne asbestos fiber results for workers Warren Abbot, Paul Crowder and Dave Shamblin during…
-
Company document · Union Carbide documents · September 2, 1982
Industrial Hygiene Monitoring Reports for Asbestos on Insulation Stripping in Building 707, to W. T. Shelton (1980-1982)
Five one-page 'Industrial Hygiene Monitoring for Asbestos' forms addressed to W. T. Shelton of the 704 Shop. They report air-sample fiber concentrations for workers stripping insulation from steam and Dowtherm lines in Building 707, with dates from…
-
Company document · Union Carbide documents · November 24, 1980
Industrial Hygiene Monitoring for Asbestos: Powerhouse Steam Line Stripping, Bldg. 704, to W. T. Shelton (1980)
One-page industrial hygiene monitoring form for asbestos dated 11/24/80. It reports personal air samples for R. E. Raines (.07 fibers/cc) and John Greenlee (.13 fibers/cc), each taken over 41 minutes in the Building 704 Powerhouse basement while…
-
Company document · Union Carbide documents · October 20, 1980
Industrial Hygiene Monitoring for Asbestos: Two Reports to W. T. Shelton on Stripping Insulation from the Dowtherm System, Bldg. 702 (1980)
Two industrial hygiene monitoring forms dated 10/20/80 reporting asbestos fiber samples taken outside Bldg. 702 while workers stripped and bagged insulation from a Dowtherm system. J. E. Hackney's sample was 3.04 fibers >5 µm/cm3 over 57 minutes,…
-
Company document · Union Carbide documents · July 3, 1980
Industrial Hygiene Monitoring for Asbestos: Cooling Tower Insulation Stripping, Building 789, to R. F. Painter (1980)
Three industrial hygiene monitoring forms for asbestos dated 7/3/80, reporting air samples taken on workers stripping and bagging cooling tower insulation in the basement of Building 789. Morning sample results were .3, .7 and .3 fibers >5 µm/cm3;…
-
Company document · Union Carbide documents · April 22, 1981
Industrial Hygiene Monitoring for Asbestos: Insulator Stripping Pipe Insulation at Bldg. 773, Reports to R. F. Painter (1981)
Two industrial hygiene monitoring forms dated 04/22/81 reporting airborne asbestos fiber sampling on 04/20/81 for two insulators stripping about 100 feet of 1-1/2" pipe insulation outside Bldg. 773. The first form reports D. C. Shamblin's results…
-
Company document · Union Carbide documents · October 5, 1978
C. W. Carman to E. R. Levy on Review Meeting of Personnel Safety and Health Training Packages (1978)
Memo dated October 5, 1978 from C. W. Carman to E. R. Levy, with copies to ten others, giving his comments on the personnel safety and health training elements discussed at a September 25, 1978 meeting. It lists suggestions from George Hurley, J. M.…