Company document · Union Carbide documents · September 2, 1987
L. S. Magelssen and H. W. Wegert to J. F. Dodd et al. on Status of Contingency Items for Asbestos Insulation Removal Upgrade, South Charleston (1987)
Two-page memorandum reporting that two contingency items attached to the May 19, 1987 health, safety and environmental endorsement of the South Charleston Asbestos Insulation Removal Upgrade-Phase I had been resolved. It discusses review of the…
-
Company document · Union Carbide documents · July 7, 1987
J. K. Corrie to H. W. Wegert and G. M. Whipple on Environmental Concerns in the South Charleston Insulation Upgrade Project, with Revised Asbestos Handling Procedure (1987)
Internal correspondence from J. K. Corrie transmitting the revised South Charleston Plant Maintenance Safety Procedure XVIII on asbestos handling. The memo says the revision addresses concerns raised in an October 30, 1986 review of the plant's…
-
Company document · Union Carbide documents · October 30, 1986
H. W. Wegert and G. M. Whipple to J. R. Dement and Others on Health, Safety and Environmental Review of the South Charleston Insulation Upgrade Project (1986)
Memorandum reporting a health, safety and environmental review of a three-year project to remove, replace and seal asbestos insulation at the South Charleston Plant. It recommends endorsement contingent on revising Maintenance Procedure XVIII to…
-
Company document · Union Carbide documents · October 30, 1986
H. W. Wegert and G. M. Whipple to J. R. Dement et al. on Health, Safety, and Environmental Review of the South Charleston Insulation Upgrade Project (1986)
Memorandum reporting a health, safety and environmental review of a three-year project to upgrade asbestos insulation at the South Charleston Plant. It recommended endorsement contingent on revising Maintenance Procedure XVIII to comply with the…
-
Company document · Union Carbide documents · May 19, 1987
L. S. Magelssen and H. W. Wegert to J. R. Dement and Others on Health, Safety and Environmental Review of the South Charleston Asbestos Insulation Removal Upgrade, Phase I (1987)
A May 19, 1987 memo recommending endorsement of Phase I of a project to remove and upgrade asbestos insulation at the South Charleston plant. The endorsement is contingent on revising Maintenance Procedure XVIII to comply with OSHA 29 CFR 1926.58…
-
Company document · Union Carbide documents · September 2, 1987
L. S. Magelssen and H. W. Wegert to J. F. Dodd and Others on Status of Contingency Items for Asbestos Insulation Removal Upgrade, South Charleston (1987)
Memorandum reporting that two contingency items attached to the May 19, 1987 endorsement of the South Charleston asbestos insulation removal upgrade (Phase I) had been resolved. It says the February 1987 asbestos maintenance procedures were reviewed…