Company document · Union Carbide documents · March 25, 1987
J. K. Corrie to Maintenance Staff Transmitting Draft Maintenance Safety Procedure XVIII, Asbestos Handling, South Charleston Plant (1987)
A March 25, 1987 cover memo from J. K. Corrie circulating a final review draft of Maintenance Safety Procedure XVIII, Asbestos Handling, for the South Charleston plant, with comments requested by April 3, 1987. The attached 20-page draft (dated…
-
Company document · Union Carbide documents · June 11, 1987
M. J. Shoger to J. K. Corrie and Others on Asbestos Enclosures and HWP Requirements Meeting (1987)
Internal Union Carbide memo announcing a June 19 meeting, sponsored by Chuck Rotthoff, with Institute, South Charleston and Sistersville personnel on plant practices for enclosures used in asbestos removal. It states there were two close calls…
-
Company document · Union Carbide documents · February 11, 1987
W. J. Vincent to J. K. Corrie Transmitting Responses to Asbestos Abatement and Removal Questions, South Charleston Plant (1987)
Internal Union Carbide memo from W. J. Vincent to J. K. Corrie forwarding answers to questions raised at a recent meeting on asbestos abatement and removal. The attached "Asbestos Management" Q&A covers negative pressure enclosures…
-
Company document · Union Carbide documents · July 7, 1987
J. K. Corrie to H. W. Wegert and G. M. Whipple on Environmental Concerns in the South Charleston Insulation Upgrade Project, with Revised Asbestos Handling Procedure (1987)
Internal correspondence from J. K. Corrie transmitting the revised South Charleston Plant Maintenance Safety Procedure XVIII on asbestos handling. The memo says the revision addresses concerns raised in an October 30, 1986 review of the plant's…
-
Company document · Union Carbide documents · February 11, 1987
W. J. Vincent to J. K. Corrie Transmitting Responses to Asbestos Abatement Questions, South Charleston Plant (1987)
Internal Union Carbide memo from W. J. Vincent to J. K. Corrie, stamped received by the Maintenance Department on Feb. 17, 1987, forwarding answers to questions on asbestos raised at a recent meeting on asbestos abatement…
-
Company document · Union Carbide documents · March 25, 1987
J. K. Corrie to J. R. Dement and Others Circulating Draft Maintenance Safety Procedure XVIII, Asbestos Handling, South Charleston Plant (1987)
…with handwritten routing note dated 3-25-87 and comments signed Bob Hull (UCC 019705) Clean copy of the same Corrie transmittal memo on Union Carbide Specialty Chemicals Division letterhead (UCC 019706) Maintenance Safety Manual XVIII…
-
Company document · Union Carbide documents · May 14, 1986
M. E. Knopp Manhour Estimate for Stripping and Re-insulating Asbestos-Insulated Tanks, Bldg. 103-216, Phase I (1986)
Handwritten memo estimating Phase I manhours (1,924 total) to strip insulation, scaffold, remove scaffolds and re-insulate tanks in Bldg. 103-216, with a page-2 breakdown by tank, each labeled "ASBESTOS". A handwritten note dated 5/13/86 recommends…
-
Company document · Union Carbide documents · May 7, 1987
W. J. Vincent to J. K. Corrie on Glove Bag Usage During Removal of Damaged Asbestos Gasket (1987)
Internal Union Carbide memo from the South Charleston Plant Safety and Health Department, following a May 4, 1987 phone conversation about removing asbestos gaskets. It states that personal exposures had been measured at or above the…