  1. Company document · Union Carbide documents · April 7, 1987

    T. L. Grittie, Industrial Hygiene Results on Asbestos Monitoring During Deinsulation of R-2 Reactor, Silanes (1987)

    Industrial hygiene results dated April 7, 1987 for breathing-zone asbestos samples taken February 10, 1987 on insulators removing insulation from reactor R-2 in the Reactor Area of Silanes inside a negative pressure enclosure. The two samples…

  2. Company document · Union Carbide documents · May 5, 1987

    R. S. Newberger and J. K. Kyle Memos on Asbestos Disposal and Ceiling Contamination at the Sistersville, WV Plant (1987)

    Two Union Carbide memoranda from the Sistersville, West Virginia plant. The first (May 5, 1987) reports that asbestos insulation was being stripped in the Silanes Department and that the burial location was full. The second (April…

  3. Company document · Union Carbide documents · May 7, 1987

    G. W. Wulfert to F. E. Dailey and Others on Future Asbestos Disposal Sites at Sistersville (1987)

    Memorandum dated May 7, 1987 stating that the Sistersville plant's asbestos disposal landfill was nearing the end of its life and that a new plan was needed. It called a meeting on May 26, 1987 at 1 PM in Building 33 to develop that plan.…

  4. Company document · Union Carbide documents · November 7, 1986

    D. A. Boggs to S. L. Curtis on Serious Asbestos Health Hazard in the Monomers North Rectification Area, Sistersville Plant (1986)

    Memo from the Sistersville Plant industrial hygienist reporting exposed, deteriorating asbestos insulation on distillation columns in the Monomers North Rectification Area and chunks of asbestos material found on the ground up to about 60 yards…

  5. Company document · Union Carbide documents · May 27, 1987

    G. W. Wulfert Minutes of the 'Future Asbestos Disposal Site(s)' Meeting, with Related Memos on the Sistersville Asbestos Landfill (1987)

    Union Carbide Sistersville, WV plant memos from May 1987 about the plant's asbestos landfill, which held asbestos insulation removed from plant equipment. The May 27 minutes record an estimate that the present landfill had about…

  6. Company document · Union Carbide documents · April 6, 1987

    T. L. Grittie Industrial Hygiene Results on Glove Bag Asbestos Insulation Removal and Transite Roof Removal (1987)

    Two Industrial Hygiene Results reports dated April 6, 1987. The first reports airborne fiber sampling of insulators removing asbestos insulation by the glove bag technique at the SSP Unit, K-36, and recommends closer scrutiny of the method. The…

  7. Company document · Union Carbide documents · January 11, 1988

    K. B. Purinton to W. C. Nycz on Three Year Plant Insulation Upgrade Program, Sistersville (1988)

    Memo from K. B. Purinton at the Sistersville, WV plant setting out criteria for insulation to be included in a three-year plant insulation upgrade program, including asbestos insulation in areas of high mechanical disturbance. It states that…

  8. Company document · Union Carbide documents · March 20, 1987

    C. A. Eddy to E. C. Buford and Others on March 19, 1987 Meeting Minutes, Methyls Columns Asbestos Insulation Removal at Sistersville (1987)

    Minutes, dated March 20, 1987, of a March 19, 1987 meeting at the Sistersville Plant to plan removal of asbestos insulation from six methyls columns. They list 19 items on the handling of each column, use of a negative pressure enclosure, area…

  9. Company document · Union Carbide documents · July 1, 1987

    T. L. Grittie Industrial Hygiene Results on Asbestos Monitoring of Insulators (Tank Farm 4) and the Poly I Control Room (1987)

    Two industrial hygiene result sheets dated July 1, 1987, reporting asbestos air sampling done in April 1987. Page 1 covers insulators using glove bags to strip T-111 in Tank Farm 4 in Silanes, and page 2 covers the Poly I control room, where…