8 results for “Union Carbide Corporation”
-
Company document · Union Carbide documents · September 2, 1987
L. S. Magelssen and H. W. Wegert to J. F. Dodd et al. on Status of Contingency Items for Asbestos Insulation Removal Upgrade, South Charleston (1987)
Two-page memorandum reporting that two contingency items attached to the May 19, 1987 health, safety and environmental endorsement of the South Charleston Asbestos Insulation Removal Upgrade-Phase I had been resolved. It discusses review of the…
-
Company document · Union Carbide documents · October 30, 1986
H. W. Wegert and G. M. Whipple to J. R. Dement et al. on Health, Safety, and Environmental Review of the South Charleston Insulation Upgrade Project (1986)
Memorandum reporting a health, safety and environmental review of a three-year project to upgrade asbestos insulation at the South Charleston Plant. It recommended endorsement contingent on revising Maintenance Procedure XVIII to comply with the…
-
Company document · Union Carbide documents · May 19, 1987
L. S. Magelssen and H. W. Wegert to J. R. Dement and Others on Health, Safety and Environmental Review of the South Charleston Asbestos Insulation Removal Upgrade, Phase I (1987)
A May 19, 1987 memo recommending endorsement of Phase I of a project to remove and upgrade asbestos insulation at the South Charleston plant. The endorsement is contingent on revising Maintenance Procedure XVIII to comply with OSHA 29 CFR 1926.58…
-
Company document · Union Carbide documents · May 31, 1984
D. A. Gosselin to John Buzzard on Laundering Asbestos-Contaminated Clothing under the OSHA Standard (1984)
Internal Union Carbide memo in which D. A. Gosselin responded to John Buzzard's letter about laundering asbestos-contaminated clothing under OSHA Standard 1910.1001. He recommended that a letter be sent to the owner of…
-
Company document · Union Carbide documents · September 2, 1987
L. S. Magelssen and H. W. Wegert to J. F. Dodd and Others on Status of Contingency Items for Asbestos Insulation Removal Upgrade, South Charleston (1987)
Memorandum reporting that two contingency items attached to the May 19, 1987 endorsement of the South Charleston asbestos insulation removal upgrade (Phase I) had been resolved. It says the February 1987 asbestos maintenance procedures were reviewed…
-
Company document · Union Carbide documents · May 19, 1987
L. S. Magelssen and H. W. Wegert to J. R. Dement and Others on Health, Safety and Environmental Review of the Asbestos Insulation Removal Upgrade, South Charleston (1987)
Memo recommending endorsement of Phase I of the asbestos insulation removal and upgrade project at the South Charleston plant. It notes that OSHA's 29 CFR 1926.58 rule, promulgated January 16, 1987, raised the cost of removal and repair. Endorsement…
-
Company document · Union Carbide documents · May 31, 1984
D. A. Gosselin to John Buzzard on Laundering Asbestos-Contaminated Clothing (1984)
Internal correspondence in which D. A. Gosselin responded to John Buzzard's letter about laundering asbestos-contaminated clothing under OSHA Standard 1910.1001. He advised that a letter be sent to the owner of Vogue-Swift Cleaners citing the…
-
Company document · Union Carbide documents · November 12, 1986
J. L. Worstell to R. L. Foster and C. H. Hancock Forwarding EPA Notice of Deficiency on Asbestos Renovation at South Charleston Plant (1986)
…EPA Region III Notice of Deficiency dated November 7, 1986, and Union Carbide's asbestos removal notification for the No. 19 Batch Still at the Mainland Chemicals Unit. The EPA letter stated the notice was incomplete…