2 results for “General Electric”
-
Court case · U.S. District Court, Northern District of Illinois · October 22, 2013 · in the opinion
Stanley v. Ameren Illinois Co. (2013)
… and decreasing the operating costs of the plant. It is not necessary to the processes that create electricity, but it is required for efficiency and safety in the operation of a power plant. During the construction…
-
Court case · Illinois Appellate Court · March 18, 1993 · in the opinion
Campbell v. AC Equipment Services Corporation, Inc. (1993)
…TGM, alleged they were employed by TGM to perform work for A.C. Equipment and Springfield's City Water, Light and Power Division at an electricity generating station known as Lakeside Two. A.C. Equipment, a…