7 results for “Union Carbide Corporation”
-
Company document · Union Carbide documents · March 25, 1987
J. K. Corrie to Maintenance Staff Transmitting Draft Maintenance Safety Procedure XVIII, Asbestos Handling, South Charleston Plant (1987)
A March 25, 1987 cover memo from J. K. Corrie circulating a final review draft of Maintenance Safety Procedure XVIII, Asbestos Handling, for the South Charleston plant, with comments requested by April 3, 1987. The attached 20-page draft (dated…
-
Company document · Union Carbide documents · June 11, 1987
M. J. Shoger to J. K. Corrie and Others on Asbestos Enclosures and HWP Requirements Meeting (1987)
Internal Union Carbide memo announcing a June 19 meeting, sponsored by Chuck Rotthoff, with Institute, South Charleston and Sistersville personnel on plant practices for enclosures used in asbestos removal. It states there were two close calls…
-
Company document · Union Carbide documents · September 1, 1987
T. G. Huff to D. J. McNeil and Others: Project Scope Document for B-303 Transitional Operation/Demolition Phase II, South Charleston Plant (1987)
Project scope document for Building 303 transitional operation and demolition at the South Charleston Plant. It describes temporary drum-handling facilities and the removal and disposal of asbestos-containing transite siding by an abatement…
-
Company document · Union Carbide documents · February 24, 1987
W. J. Vincent to All Department Heads on Labelling of Asbestos Materials, with Standard Practice SH-256 on Removal and Handling of Asbestos-Containing Insulation (1987)
A February 1987 internal memo from the South Charleston Plant Safety and Health Department told department heads that asbestos warning labels were now required on installed asbestos products whenever feasible and gave the supplier and cost. Attached…
-
Company document · Union Carbide documents · February 11, 1987
W. J. Vincent to J. K. Corrie Transmitting Responses to Asbestos Abatement Questions, South Charleston Plant (1987)
Internal Union Carbide memo from W. J. Vincent to J. K. Corrie, stamped received by the Maintenance Department on Feb. 17, 1987, forwarding answers to questions on asbestos raised at a recent meeting on asbestos abatement…
-
Company document · Union Carbide documents · August 23, 1987
T. G. Huff to S. W. Drake and Others: Project Scope Document for B-303 Demolition and Transite Siding Removal, South Charleston Plant (1987)
Project scope document for demolishing part of Building 303 at the South Charleston Plant and replacing asbestos-containing transite siding on the Chemical Mixing Unit Slurry Bay with insulated metal panels. It sets out mechanical, electrical and…
-
Company document · Union Carbide documents · March 25, 1987
J. K. Corrie to J. R. Dement and Others Circulating Draft Maintenance Safety Procedure XVIII, Asbestos Handling, South Charleston Plant (1987)
…with handwritten routing note dated 3-25-87 and comments signed Bob Hull (UCC 019705) Clean copy of the same Corrie transmittal memo on Union Carbide Specialty Chemicals Division letterhead (UCC 019706) Maintenance Safety Manual XVIII…