Company document · Union Carbide documents · September 5, 1986
T. E. Hanning to S. W. Clark and Others on Asbestos Update: Union Support for Proposed EPA Ban (1986)
…marked 'For Your Information', reporting that labor unions were endorsing a proposed EPA asbestos ban and contending that OSHA's 0.2 fiber/cc limit gave insufficient worker protection. It also summarizes the proposed EPA rule…
-
Company document · Union Carbide documents · March 21, 1984
G. D. Twait to Wayne Williams on November 1983 Revisions to SH-256, Removal and Handling of Asbestos-Containing Insulation Material (1984)
A handwritten 1984 note from G. D. Twait to Wayne Williams confirming that the asbestos permissible exposure limit in the November 1983 revision of SH-256 would stay at 0.5 fibers/cc, with attached material. The attachments are the OSHA emergency…
-
Company document · Union Carbide documents · September 2, 1987
L. S. Magelssen and H. W. Wegert to J. F. Dodd et al. on Status of Contingency Items for Asbestos Insulation Removal Upgrade, South Charleston (1987)
Two-page memorandum reporting that two contingency items attached to the May 19, 1987 health, safety and environmental endorsement of the South Charleston Asbestos Insulation Removal Upgrade-Phase I had been resolved. It discusses review of the…
-
Company document · Union Carbide documents · June 28, 1985
W. C. Young to Plant Managers Department on Asbestos Exposure Effects and Potential of Non-Insulator Crafts, with Plant 514 Asbestos Dust Measurement Printouts (1985)
Internal memo of June 28, 1985 from the South Charleston Plant to the Managers Department stating that plant asbestos dust measurements were below OSHA limits, but the writer questioned whether any level of inhalation exposure is safe without…
-
Company document · Union Carbide documents · October 28, 1986
T. E. Hanning to Recipient on Review of South Charleston Plant Procedures for Removal and Disposal of Asbestos Materials (1986)
Memorandum from T. E. Hanning reviewing updates to the South Charleston plant's 514 Maintenance Department procedure for handling and disposing of asbestos insulation, following the July 1986 OSHA revision. It sets out the revised exposure limit and…
-
Company document · Union Carbide documents · October 30, 1986
H. W. Wegert and G. M. Whipple to J. R. Dement and Others on Health, Safety and Environmental Review of the South Charleston Insulation Upgrade Project (1986)
Memorandum reporting a health, safety and environmental review of a three-year project to remove, replace and seal asbestos insulation at the South Charleston Plant. It recommends endorsement contingent on revising Maintenance Procedure XVIII to…
-
Company document · Union Carbide documents · October 30, 1986
H. W. Wegert and G. M. Whipple to J. R. Dement et al. on Health, Safety, and Environmental Review of the South Charleston Insulation Upgrade Project (1986)
Memorandum reporting a health, safety and environmental review of a three-year project to upgrade asbestos insulation at the South Charleston Plant. It recommended endorsement contingent on revising Maintenance Procedure XVIII to comply with the…
-
Company document · Union Carbide documents · February 1, 1984
C. A. McNeill to J. B. Mickey Transmitting Draft Safety and Health Requirements for Contractors, Sistersville Plant (1984)
A February 1, 1984 cover memo from C. A. McNeill to J. B. Mickey attaching a draft package of three documents on safety and health requirements for contractors at the Sistersville Plant. The package includes contractor rules, a list of potential…
-
Company document · Union Carbide documents · November 7, 1986
D. A. Boggs to S. L. Curtis on Serious Asbestos Health Hazard in the Monomers North Rectification Area, Sistersville Plant (1986)
Memo from the Sistersville Plant industrial hygienist reporting exposed, deteriorating asbestos insulation on distillation columns in the Monomers North Rectification Area and chunks of asbestos material found on the ground up to about 60 yards…
-
Company document · Union Carbide documents · October 29, 1986
W. V. Summers to D. Liebeskind on the Sistersville Asbestos Insulation Upgrade Project (1986)
Memo dated October 29, 1986 from W. V. Summers at the Sistersville, WV plant to D. Liebeskind, with copies to six others, giving comments on the plant's asbestos insulation upgrade project. It describes damaged installed asbestos insulation as the…
-
Company document · Union Carbide documents · November 7, 1986
J. F. Dodd to D. A. Gosselin and Others Transmitting the South Charleston Plant Insulation Asbestos Upgrade Outline of Project (1986)
Cover memo dated November 7, 1986 transmitting for review an Outline of Project for a plantwide asbestos insulation upgrade at the South Charleston, WV plant, described as a high-priority Safety/Health Program. The attached outline describes the…
-
Company document · Union Carbide documents · September 5, 1986
T. E. Hanning to S. W. Clark and Others on an Asbestos Update: Proposed EPA Ban and OSHA Exposure Limit (1986)
One-page memorandum "for your information" reporting that labor unions were endorsing a proposed EPA asbestos ban and contended OSHA's 0.2 fibers per cubic centimeter limit gave insufficient protection. It also summarized the proposed…
-
Company document · Union Carbide documents · May 21, 1984
J. R. Buzzard to D. A. Gosselin on Cleaning of Insulators Clothing at Vogue-Swift Cleaners (1984)
Internal Union Carbide correspondence from the Purchasing Department confirming a phone conversation about cleaning insulators' clothing at Vogue-Swift Cleaners in Marietta, Ohio. It outlines the procedure: purchase order, labeled black polyethylene bags, a phone call…
-
Company document · Union Carbide documents · May 21, 1984
J. R. Buzzard to D. A. Gosselin on Cleaning of Insulators Clothing at Vogue-Swift Cleaners, with OSHA Asbestos Rule Excerpt and Removal Checklist (1984)
An internal Union Carbide letter dated May 21, 1984, in which the Purchasing Agent outlined how clothing worn by insulators was sent for cleaning at Vogue-Swift Cleaners in Marietta, Ohio, and asked whether OSHA requirements…
-
Company document · Union Carbide documents · May 19, 1987
L. S. Magelssen and H. W. Wegert to J. R. Dement and Others on Health, Safety and Environmental Review of the South Charleston Asbestos Insulation Removal Upgrade, Phase I (1987)
A May 19, 1987 memo recommending endorsement of Phase I of a project to remove and upgrade asbestos insulation at the South Charleston plant. The endorsement is contingent on revising Maintenance Procedure XVIII to comply with OSHA 29 CFR 1926.58…
-
Company document · Union Carbide documents · January 9, 1987
C. R. Rotthoff to W. J. Vincent on South Charleston Provisions for Asbestos Material Removal and Disposal (1987)
Internal correspondence in which C. R. Rotthoff commented on W. J. Vincent's South Charleston asbestos removal document, saying it assumed no technology exists to keep asbestos below the PEL. He suggested identifying which steps are mandatory…
-
Company document · Union Carbide documents · September 2, 1987
L. S. Magelssen and H. W. Wegert to J. F. Dodd and Others on Status of Contingency Items for Asbestos Insulation Removal Upgrade, South Charleston (1987)
Memorandum reporting that two contingency items attached to the May 19, 1987 endorsement of the South Charleston asbestos insulation removal upgrade (Phase I) had been resolved. It says the February 1987 asbestos maintenance procedures were reviewed…
-
Company document · Union Carbide documents · March 18, 1986
T. L. Grittie to D. A. Boggs and Others on McCrone Analysis of Jaxsan Insulation Samples at Sistersville (1986)
Memo from T. L. Grittie transmitting McCrone Environmental Services' analysis of five Jaxsan insulation samples from the Sistersville plant. The memo reports 7-15% chrysotile asbestos, higher than the supplier had stated, and says the material…
-
Company document · Union Carbide documents · January 9, 1987
C. R. Rotthoff to W. J. Vincent Transmitting Comments on South Charleston Provisions for Asbestos Material Removal and Disposal (1987)
Internal memo from C. R. Rotthoff to W. J. Vincent commenting on the South Charleston plant's draft asbestos removal document, suggesting that exposure be kept below the PEL where possible and that steps required because the PEL will be exceeded be…
-
Company document · Union Carbide documents · March 18, 1986
T. L. Grittie to D. A. Boggs and Others on McCrone Analysis of Jaxsan Insulation Samples for Asbestos (1986)
Memo from the Sistersville plant industrial hygienist transmitting McCrone Environmental Services' analysis of five Jaxsan samples. It reports 7-15% chrysotile, higher than the supplier indicated, says the IH group will monitor insulators during…