23 results for “Union Carbide Corporation”, page 1 of 2
-
Company document · Union Carbide documents · February 14, 1984
C. R. Gillespie to T. G. Swanson on Asbestos Handling Procedures Committee Feedback (1984)
Memo from the chairperson of the Asbestos Handling Procedures Committee reporting the results of a review with T. G. Swanson and W. C. Young of the committee's recommendations. It lists accepted changes and completion dates covering maintenance…
-
Company document · Union Carbide documents · February 11, 1985
W. L. Thomas to W. E. Ballard and Others Calling a Meeting on the Asbestos Insulation Replacement Project, with J. G. Roy's No. 2 Steam Plant Proposal (1985)
A February 11, 1985 memorandum from W. L. Thomas called a February 21, 1985 meeting to plan an asbestos insulation replacement project at the South Charleston plant and attached a December 27, 1984 proposal by J. G. Roy. Roy's proposal outlined a…
-
Company document · Union Carbide documents · March 27, 1985
J. G. Roy to J. F. Dodd on the Plant Project to Eliminate Asbestos Exposure at South Charleston (1985)
Memo from J. G. Roy to J. F. Dodd about a project to eliminate asbestos exposure at the South Charleston plant, starting with the No. 2 Steam Plant. It summarizes a February 21 kickoff meeting and a meeting with an insulating contractor, objects to…
-
Company document · Union Carbide documents · March 25, 1987
J. K. Corrie to Maintenance Staff Transmitting Draft Maintenance Safety Procedure XVIII, Asbestos Handling, South Charleston Plant (1987)
A March 25, 1987 cover memo from J. K. Corrie circulating a final review draft of Maintenance Safety Procedure XVIII, Asbestos Handling, for the South Charleston plant, with comments requested by April 3, 1987. The attached 20-page draft (dated…
-
Company document · Union Carbide documents · December 27, 1984
J. G. Roy to T. G. Swanson on Asbestos Insulation Replacement at the No. 2 Steam Plant, South Charleston, with Attached Elimination Program and Related Notices (1984)
A December 27, 1984 memo from J. G. Roy to T. G. Swanson transmitted a proposal to phase out asbestos insulation at the No. 2 Steam Plant, South Charleston, with an attached 49-item work list. Later pages hold an April 1985 memo on protective gear…
-
Company document · Union Carbide documents · June 28, 1985
W. C. Young to Plant Managers Department on Asbestos Exposure Effects and Potential of Non-Insulator Crafts, with Plant 514 Asbestos Dust Measurement Printouts (1985)
Internal memo of June 28, 1985 from the South Charleston Plant to the Managers Department stating that plant asbestos dust measurements were below OSHA limits, but the writer questioned whether any level of inhalation exposure is safe without…
-
Company document · Union Carbide documents · September 25, 1986
W. J. Vincent to J. K. Corrie and Others on the New Asbestos Construction Standard (1986)
A September 1986 memo from W. J. Vincent transmitting a summary of the new OSHA Asbestos Construction Industry Standard. The attached summary covers the 0.2 f/cc permissible exposure limit, the 0.1 f/cc action level, monitoring, respirators,…
-
Company document · Union Carbide documents · February 25, 1985
I. L. Beckett to W. E. Ballard et al. on Minutes of the Asbestos Insulation Replacement Project, Phase I Meeting, South Charleston Plant (1985)
Memorandum giving minutes of a February 21, 1985 meeting on a project to repair and replace asbestos insulation at the South Charleston Plant. It records the 1985 funding limit, the choice of six departments to start with, the plan to use…
-
Company document · Union Carbide documents · July 29, 1987
S. B. Kovach to T. G. Swanson Transmitting SHARE Inspection Results, with Audit Team Reports, South Charleston Plant (1987)
Cover letter from the SHARE Coordinator at the South Charleston Plant to T. G. Swanson transmitting findings of a SHARE inspection held July 29, 1987. It sets a 90-day deadline to address deficiencies and 30-day progress updates. Three attached…
-
Company document · Union Carbide documents · December 16, 1983
W. C. Young to T. G. Swanson on the Stay of OSHA's Emergency Temporary Standard for Asbestos (1983)
A one-page memorandum reporting that the Fifth Circuit Court of Appeals granted the Asbestos Information Association's request to stay OSHA's emergency temporary standard on occupational asbestos exposure. It states that the order bars OSHA from…
-
Company document · Union Carbide documents · April 5, 1984
W. C. Young to T. G. Swanson on Court Ruling Disallowing the OSHA Asbestos Emergency Temporary Standard (1984)
A one-page memorandum from W. C. Young to T. G. Swanson, with copies to others, reproducing a summary from Occupational Safety and Health Reporter. The summary reports that the Fifth Circuit struck down OSHA's emergency asbestos standard. Young…
-
Company document · Union Carbide documents · December 15, 1983
W. C. Young to T. G. Swanson on the Amended OSHA Asbestos Standard at South Charleston, with OSHA Exposure Estimates and Emergency Standard Text (1983)
A December 15, 1983 memorandum from W. C. Young summarizes the points of OSHA's emergency temporary asbestos standard (effective November 4, 1983) that would affect plant operations. For each change (the 0.5 f/cc limit, employee training, respirator…
-
Company document · Union Carbide documents · August 12, 1987
S. B. Kovach to D. H. Ott Transmitting SHARE Inspection Results, with Audit Team's Report for Polyols Insulation (1987)
Cover letter from the South Charleston Plant SHARE Coordinator to D. H. Ott forwarding findings from the SHARE inspection of August 12, 1987. It sets goals of addressing deficiencies within 90 days and sending 30-day progress updates, and includes a…
-
Company document · Union Carbide documents · April 17, 1985
I. L. Beckett to J. F. Dodd and Others on Project Scope for Safety/Health Insulation, No. 2 Powerhouse, Building 151 (1985)
Memorandum setting out a project scope for removing, replacing or sealing deteriorated asbestos insulation in the No. 2 Powerhouse (Building 151) at South Charleston, West Virginia. It describes the capital and removal work, safety and environmental…
-
Company document · Union Carbide documents · March 25, 1987
J. K. Corrie to J. R. Dement and Others Circulating Draft Maintenance Safety Procedure XVIII, Asbestos Handling, South Charleston Plant (1987)
…with handwritten routing note dated 3-25-87 and comments signed Bob Hull (UCC 019705) Clean copy of the same Corrie transmittal memo on Union Carbide Specialty Chemicals Division letterhead (UCC 019706) Maintenance Safety Manual XVIII…
-
Company document · Union Carbide documents · December 15, 1983
W. C. Young to T. G. Swanson on the Amended OSHA Asbestos Standard (1983)
Memorandum summarizing the points of OSHA's amended emergency temporary asbestos standard, effective November 4, 1983, most likely to affect plant operations. It lists the changes (the permissible exposure limit cut from 2 to 0.5 f/cc, training, and…
-
Company document · Union Carbide documents · March 4, 1987
R. G. Link to B. N. Gliatta on the Asbestos Removal Program at the South Charleston Plant (1987)
Internal Union Carbide correspondence in which R. G. Link told B. N. Gliatta he wanted to move ahead with the asbestos removal program at the South Charleston Plant. He listed five steps: assigning a manager, pushing…
-
Company document · Union Carbide documents · July 26, 1985
W. E. Ballard to R. G. Link on Asbestos Insulation at the South Charleston Plant (1985)
Internal memo reporting a follow-up with Corporate HS&EA on removing asbestos insulation at plant facilities. It states the corporation has no requirements beyond government regulations, summarizes the asbestos programs at Seadrift and Institute, and…
-
Company document · Union Carbide documents · July 14, 1983
Bill Young to Maintenance Area Superintendents Forwarding OSHA Plans Asbestos Exposure Limit Reduction Report (1983)
A one-page Union Carbide South Charleston Plant internal memo transmitting an attached Occupational Safety & Health Reporter article on OSHA's plans to lower the asbestos exposure limit. The attached BNA report (July 7, 1983) states…
-
Company document · Union Carbide documents · June 17, 1987
S. B. Kovach to D. H. Ott Transmitting South Charleston Plant SHARE Inspection Results, with Audit Team Reports Noting Exposed Asbestos Insulation (1987)
A June 17, 1987 cover letter from the SHARE Coordinator at the South Charleston Plant to D. H. Ott forwarding findings of a SHARE inspection, stating that deficiencies must be addressed within 90 days and progress updates sent every 30 days. The…