10 results for “Union Carbide Corporation”
-
Company document · Union Carbide documents · December 15, 1983
Union Carbide Sistersville Plant Capital Work Order 380-564, Safety & Health – Insulation (Asbestos Insulation Replacement), with Handwritten Notes (1983)
Capital work order package for a $500,000 project to repair or replace exposed asbestos insulation in the Steam Plant and Monomers Area of the Sistersville, WV plant, replacing it with calcium silicate insulation. It includes the work order form, an…
-
Company document · Union Carbide documents · 1985
Union Carbide Specialty Chemicals Division 838 Removal Request for Asbestos Insulation Control, Phase II, South Charleston Plant (1985)
A four-page Union Carbide 838 Removals and Retirements request (Job NP-1020, Request 514-0471) for a $182,000 project to remove asbestos insulation from idle equipment and lines at the South Charleston Plant. It…
-
Company document · Union Carbide documents · 1985
Union Carbide Specialty Chemicals Division Engineering Request NP-1020 for Asbestos Insulation Control, Phase II, South Charleston Plant (1985)
Engineering request and job authorization (NP-1020, request 514-0471) for a $182,000 project to remove asbestos insulation from idle equipment and lines at the South Charleston Plant. It gives occupational health as the justification, cites the OSHA…
-
Company document · Union Carbide documents · September 1986
Removals & Retirements Work Order 838-2391: Asbestos Insulation Control, Upper Island Chemical Complex, South Charleston Plant (1986)
A capital work order (Removals & Retirements, job NP-2147, request 514-0544) authorizing $26,000 to remove asbestos insulation from idle equipment and lines in the Upper Island DAA/MSO facilities and unused Ethanol DSP facilities at the South…
-
Company document · Union Carbide documents · December 9, 1986
J. F. Dodd Transmittal of Work Order Request for Asbestos Insulation Removal at the Oxide Adducts Unit, South Charleston Plant (1986)
A December 9, 1986 transmittal memo forwards an approved Work Order Request (514-0560) for removing and replacing asbestos insulation in the Oxide Adducts Unit at the South Charleston Plant. The attached three-page work order gives a total estimate…
-
Company document · Union Carbide documents · May 28, 1987
J. F. Dodd to W. D. Bradbury, Jr. and M. G. Dwyer transmitting Work Order Request 514-0586, Asbestos Insulation Upgrade Phase I, South Charleston Plant (1987)
A cover memo transmits a locally approved capital work order request for a $900,000 capital and $270,000 expense project to upgrade asbestos insulation at the South Charleston Plant. The attached 8-page request gives the justification as…
-
Company document · Union Carbide documents · November 7, 1986
J. F. Dodd to D. A. Gosselin and Others Transmitting the South Charleston Plant Insulation Asbestos Upgrade Outline of Project (1986)
Cover memo dated November 7, 1986 transmitting for review an Outline of Project for a plantwide asbestos insulation upgrade at the South Charleston, WV plant, described as a high-priority Safety/Health Program. The attached outline describes the…
-
Company document · Union Carbide documents · May 13, 1986
Joseph F. Dodd to J. R. Dement and S. Rossi on the South Charleston Plant Asbestos Insulation Upgrade Project, with Draft Outline of Project (1986)
A May 13, 1986 cover memo from Joseph F. Dodd transmitting a draft Outline of Project for a plant-wide asbestos insulation upgrade at the South Charleston, WV plant. The memo and draft describe a $4.5 million, three-year project to remove asbestos…
-
Company document · Union Carbide documents · May 13, 1986
Joseph F. Dodd to J. R. Dement and S. Rossi Transmitting Draft Outline of Project for South Charleston Plant Asbestos Insulation Upgrade (1986)
A cover memo from Joseph F. Dodd transmitting a draft Outline of Project for a plant-wide asbestos insulation upgrade at the South Charleston, WV plant, followed by the draft outline. The outline describes the scope, a three-year schedule through…
-
Company document · Union Carbide documents · November 7, 1986
J. F. Dodd to D. A. Gosselin and Others Transmitting the South Charleston Plant Insulation Asbestos Upgrade Outline of Project (1986)
A November 7, 1986 transmittal memo from Joseph F. Dodd circulating the Outline of Project for a plantwide asbestos insulation upgrade at the South Charleston Plant, with a handwritten note asking who would perform the work. The attached outline…