No fee unless we recover compensation for your family Text size 833-4-ASBESTOS (833-427-2378) Free Case Review

Search

15 results for “Union Carbide Corporation”

  1. Company document · Union Carbide documents · April 29, 1986

    D. R. Stokely to Dr. D. L. Liebeskind Transmitting Action Plan for the South Charleston Chemical Mixing Dept. Safety/Health Survey (1986)

    Internal Union Carbide memo from the South Charleston Plant transmitting an action plan that responds to concerns raised in the July 15-19, 1985 operational safety/health survey of the Chemical Mixing Department (514). It lists…

  2. Company document · Union Carbide documents · February 3, 1986

    J. L. Worstell to J. R. D. on Asbestos Conditions at Plant 514, with R. G. Link's Cover Memo on the Corporate Environmental Audit of Plant 514 (1986)

    Page 1 is a February 3, 1986 memo from the South Charleston Plant Environmental Protection department, signed by 'JLW', to 'Jim' about asbestos conditions at Plant 514 found in a corporate EP audit about a year and a half earlier, with a suggestion…

  3. Company document · Union Carbide documents · September 1, 1987

    T. G. Huff to J. F. Dodd and Others, Project Scope Document for Building 303 Demolition, Phase III, South Charleston Plant (1987)

    Project scope document for the second-stage demolition of Building 303 at the South Charleston plant, to clear space for truck trailers serving the new Drumming Center. It describes the phased work and the removal of asbestos pipe insulation and…

  4. Company document · Union Carbide documents · September 1, 1987

    T. G. Huff to D. J. McNeil and Others: Project Scope Document for B-303 Transitional Operation/Demolition Phase II, South Charleston Plant (1987)

    Project scope document for Building 303 transitional operation and demolition at the South Charleston Plant. It describes temporary drum-handling facilities and the removal and disposal of asbestos-containing transite siding by an abatement…

  5. Company document · Union Carbide documents · August 10, 1984

    D. B. Howard to R. H. Stodghill and D. R. Stokely on Winter Preparations for Silicones II (1984)

    Area 5 Maintenance internal correspondence asking the Silicones II staff to list equipment repairs, insulation work and facility repairs needed to prepare for winter. The memo said maintenance would then prepare a Ghant chart of expected completion…

  6. Company document · Union Carbide documents · July 22, 1987

    S. B. Kovach to D. R. Stokely Transmitting SHARE Inspection Results, South Charleston Plant (1987)

    Cover letter from the South Charleston Plant SHARE Coordinator sending D. R. Stokely the findings of a SHARE inspection held July 22, 1987, and setting program goals for correcting deficiencies. It has a 30/60/90-day progress update block and…

  7. Company document · Union Carbide documents · August 23, 1987

    T. G. Huff to S. W. Drake and Others: Project Scope Document for B-303 Demolition and Transite Siding Removal, South Charleston Plant (1987)

    Project scope document for demolishing part of Building 303 at the South Charleston Plant and replacing asbestos-containing transite siding on the Chemical Mixing Unit Slurry Bay with insulated metal panels. It sets out mechanical, electrical and…

  8. Company document · Union Carbide documents · November 7, 1986

    J. F. Dodd to D. A. Gosselin and Others Transmitting the South Charleston Plant Insulation Asbestos Upgrade Outline of Project (1986)

    Cover memo dated November 7, 1986 transmitting for review an Outline of Project for a plantwide asbestos insulation upgrade at the South Charleston, WV plant, described as a high-priority Safety/Health Program. The attached outline describes the…

  9. Company document · Union Carbide documents · November 26, 1984

    W. E. Chambers and C. C. Smith, Jr. to W. H. Joyce, D. Liebeskind and R. G. Link Transmitting the South Charleston, WV Environmental Compliance Audit Report (1984)

    Cover letter transmitting the final corporate environmental compliance audit report for the South Charleston, WV facility, audited August 27-30, 1984. It asks for prompt good-faith correction of noncompliance items. The attached page is a rotated…

  10. Company document · Union Carbide documents · March 6, 1987

    D. R. Stokely to R. G. Link Transmitting Action Plan Update on 514 Chemical Mixing Department Safety/Health Survey, with Asbestos Insulation Items (1987)

    A one-page transmittal memo from D. R. Stokely to R. G. Link, copied to ten others, attaches an update on the action plan responding to the July 1985 operational safety/health survey of Plant 514 (Chemical Mixing Department). The two attached pages…

  11. Company document · Union Carbide documents · 1984

    South Charleston Plant Winterization Insulation Program: T. G. West Cover Memo, R. G. Link Memo and Weekly Status Reports (1984)

    Compilation of 1984 internal Union Carbide South Charleston Plant papers on winterization insulation work. It contains a Nov. 1, 1984 cover memo from T.G. West to J.R. Dean transmitting a status report, an Aug…

  12. Company document · Union Carbide documents · March 4, 1987

    R. G. Link to B. N. Gliatta on the Asbestos Removal Program at the South Charleston Plant (1987)

    Internal Union Carbide correspondence in which R. G. Link told B. N. Gliatta he wanted to move ahead with the asbestos removal program at the South Charleston Plant. He listed five steps: assigning a manager, pushing…

  13. Company document · Union Carbide documents · July 26, 1985

    W. E. Ballard to R. G. Link on Asbestos Insulation at the South Charleston Plant (1985)

    Internal memo reporting a follow-up with Corporate HS&EA on removing asbestos insulation at plant facilities. It states the corporation has no requirements beyond government regulations, summarizes the asbestos programs at Seadrift and Institute, and…

  14. Company document · Union Carbide documents · November 7, 1986

    J. F. Dodd to D. A. Gosselin and Others Transmitting the South Charleston Plant Insulation Asbestos Upgrade Outline of Project (1986)

    A November 7, 1986 transmittal memo from Joseph F. Dodd circulating the Outline of Project for a plantwide asbestos insulation upgrade at the South Charleston Plant, with a handwritten note asking who would perform the work. The attached outline…

  15. Company document · Union Carbide documents · October 26, 1987

    S. B. Kovach to P. R. Desai and Others Transmitting SHARE Inspection Results, South Charleston Plant (1987)

    Cover letter dated October 26, 1987 from the SHARE Coordinator at the South Charleston, West Virginia plant, sending department heads the findings of the October 14, 1987 SHARE inspection and setting a 90-day deadline to address deficiencies with…